PMP Quiz 02 March 2018

Your role in the project includes helping to resolve problems; making recommendations regarding priorities; accelerating activities to meet the target schedule; promoting communications among project team members; and helping management monitor the project’s progress on a regular basis. Most of the people working on your project are scientists or technical experts. You are working in which of the following types of organizational structures?
  • Task force
  • Balanced matrix
  • Project expeditor
  • Project coordinator