PMP Quiz 13 February 2018

As a project manager, you recognize the importance of actively engaging key project stakeholders on a project. You have prepared an analysis of your stakeholders early in your project and classified them according to their interest, influence, and involvement in your project. You want to now—
  • Focus on relationships necessary to ensure success
  • Assess stakeholder legitimacy
  • Determine the urgency that each stakeholder requires when he or she requests information about the project
  • Focus on each stakeholder’s power relevant to the project